Financial News

Rock Tech Files Revised Technical Report on SEDAR



Vancouver, BC, Canada - TheNewswire - April 21, 2021 - Rock Tech Lithium Inc. (the "Company" or “Rock Tech”) (TSXV:RCK) (OTC:RCKTF) (Frankfurt:RJIB) announces that, further to previous news releases on November 4, December 10 and December 18, 2020, the Company has filed a revised Technical Report on SEDAR.  

 

The Technical Report titled, “Preliminary Economic Assessment for an Integrated Lithium Hydroxide Operation from the Georgia Lake Lithium Project, Northwest Ontario, Canada” has an effective date of March 15, 2021, and is a revision of the Technical Report, with an effective date of October 30, 2020, previously filed on November 9, 2020.

 

A comparison of the March 15, 2021, Preliminary Economic Assessment (“PEA”) and the previously filed Technical Report is presented in the following table:

 
 

Technical Reports

 

October 30, 2020

March 15, 2021

Resource Estimate:

   

Measured Resources

1.89 MT @ 1.04% Li2O

2.31 MT @ 1.04% Li2O

Indicated Resources

4.68 MT @ 1.00% Li2O

4.31 MT @ 0.99% Li2O

M+I Resources

6.57 MT @ 1.01% Li2O

6.62 MT @ 1.01% Li2O

Inferred Resources

6.72 MT @ 1.16% Li2O

6.68 MT @ 1.16% Li2O

Preliminary Economic Assessment:

   

Operating expenses (USD/tonne LiOH)

$5,956

$6,266

IRR (%)

24.2%

21.9%

IRR (% - after tax)

21.7%

19.6%

NPV (USD)

$335m

$289m

NPV (USD - after tax)

$270m

$230m

  
The PEA is preliminary in nature, includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves and there is no certainty that the PEA will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

 

As part of the revised PEA, P&E Mining Consultants Inc. (“P&E”) recommended and reviewed contemporary approaches to geostatistical Mineral Resource classification, the compliant cut-off grade determination from PEA parameters, recommended flatter open pit slopes and executable mine designs, and suggested minor modifications to the process plant flowsheet. These changes resulted in modest increases in both the confidence of the Mineral Resource at Georgia Lake and the estimated operating expenses per tonne of lithium hydroxide. While the revised operating expenses demonstrate the potential for Georgia Lake to be among the lowest cost producers of lithium hydroxide, the Company plans further optimization work as part of the planned Pre-Feasibility Study (“PFS”) and is optimistic further improvements in operating expenses can be achieved.

 

The scientific and technical disclosure included in this news release has been reviewed and approved by Eugene Puritch, P.Eng, FEC, CET president of P&E and an independent Qualified Person under National Instrument 43-101 Standards of Disclosure of Mineral Projects ("NI 43-101").

 

On behalf of the Board of Directors,

 

"Dirk Harbecke "
Dirk Harbecke
Chairman of the Board of Directors

For further information, please contact:

Brad Barnett
Chief Financial Officer
Rock Tech Lithium Inc.
777 Hornby Street, Suite 600
Vancouver, B.C., V6Z 1S4
Telephone: (778) 358-5200
Facsimile: (604) 670-0033
Email: bbarnett@rocktechlithium.com

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Statements included in this announcement, including statements concerning our plans, intentions and expectations, which are not historical in nature are intended to be, and are hereby identified as, "forwardlooking statements".  Forwardlooking statements may be identified by words including "anticipates", "believes", "intends", "estimates", "expects" and similar expressions.  The Company cautions readers that forwardlooking statements, including without limitation those relating to the Company's future operations and business prospects, are subject to certain risks and uncertainties that could cause actual results to differ materially from those indicated in the forwardlooking statements.

Copyright (c) 2021 TheNewswire - All rights reserved.

Data & News supplied by www.cloudquote.io
Stock quotes supplied by Barchart
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms and Conditions.

Use the myMotherLode.com Keyword Search to go straight to a specific page

Popular Pages

  • Local News
  • US News
  • Weather
  • State News
  • Events
  • Traffic
  • Sports
  • Dining Guide
  • Real Estate
  • Classifieds
  • Financial News
  • Fire Info
Feedback