SECURITIES AND
EXCHANGE COMMISSION
WASHINGTON, DC 20549
FORM 8-K
CURRENT REPORT
PURSUANT TO
SECTION 13 OR 15(d) OF THE
SECURITIES EXCHANGE ACT OF 1934
Date of Report (Date of earliest event reported) December
13, 2002
|
|
Exact name of registrants as specified in |
|
|
Commission |
|
their charters, address of principal executive |
|
IRS Employer |
File Number |
|
offices and registrants' telephone number |
|
Identification Number |
1-14465 |
|
IDACORP, Inc. |
|
82-0505802 |
1-3198 |
|
Idaho Power Company |
|
82-0130980 |
|
|
1221 W. Idaho Street |
|
|
|
|
Boise, ID 83702-5627 |
|
|
|
|
(208) 388-2200 |
|
|
|
|
|
|
|
State or Other Jurisdiction of Incorporation: Idaho |
None |
Former name or former address, if changed since last report. |
IDACORP, Inc.
IDAHO POWER COMPANY
Form 8-K
Items 1 through 4 and 6, 8 and 9 are inapplicable and have
been omitted herefrom.
Item 5. OTHER EVENTS AND REGULATION FD DISCLOSURE
Idaho Power notified the United States Fish and Wildlife
Service (USFWS) on December 13, 2002 of the Company's intent to withdraw its
petitions to remove two species of snails from the federal endangered species
list. The State of Idaho and the
Company in July and October of this year petitioned the USFWS to delist the
Bliss Rapids Snail and the Idaho Springsnail.
Idaho Power said that Company biologists had discovered some
inconsistencies in field data collected by the Company over an eight-year
period, the macro invertebrate database into which the field data was entered
and the use of the database in preparation of snail studies used to support the
petitions for delisting the two snail species.
The data was collected and the database created in conjunction with the
Company's efforts to relicense five of its hydroelectric projects on the mid-Snake
River.
The Company said that it would contract with an independent
scientist to review the procedures used to collect the snail data, the field
data used to create the database, the database itself and its use in preparing
the snail studies. The Company now is
in the process of selecting that scientist.
Upon completion of the independent review the Company, in conjunction
with the State, will decide whether to once again petition for delisting.
Idaho Power is currently involved in renewing five federal
licenses for its hydroelectric projects in the mid-Snake region. Those projects include the Upper Salmon
Falls, Lower Salmon Falls, Bliss, Shoshone Falls and C.J. Strike Dams
("mid-Snake Projects"). The
potential impact of the operation of the mid-Snake Projects on the snails
listed on the federal endangered species list has raised some operating issues
in the relicensing process and Idaho Power has included in the record at the
Federal Energy Regulatory Commission (FERC) the snail studies used to support
the petitions for delisting.
Idaho Power has notified the FERC of this matter and has
requested that FERC defer taking any action in the mid-Snake Projects'
relicensing proceeding until the Company has had the opportunity to complete
the independent review. The Company expected to receive new FERC licenses for
these projects before year-end. The
Company now believes that these licenses are more likely to be issued in 2003.
If the FERC determines that operation of the Company's
mid-Snake Projects adversely impacts the listed snails, they may impose
operating conditions which could result in the loss of peaking capacity. The cost of replacing this peaking capacity
will vary depending upon market conditions and the replacement option selected.
Certain statements contained in this Current Report on Form
8-K, including statements with respect to future earnings, ongoing operations
and financial conditions, are "forward-looking statements" within the
meaning of the federal securities laws.
Although IDACORP and Idaho Power Company believe that the expectations
and assumptions reflected in these forward-looking statements are reasonable,
these statements involve a number of risks and uncertainties, and actual
results may differ materially from the results discussed in the statements. Important factors that could cause actual
results to differ materially from the forward-looking statements include: capacity and fuel; weather variations
affecting customer energy usage; operating performance of plants and other
facilities; environmental conditions and requirements; system conditions and
operating costs; changes in governmental policies; and regulatory actions,
including those of the FERC, the Idaho Public Utilities Commission, and the
Oregon Public Utilities Commission, with respect to allowed rates of return,
industry and rate structure, acquisition and disposal of assets and facilities,
operation and construction of plant facilities, recovery of purchased power and
other capital investments, and present or prospective wholesale and retail competition
(including but not limited to retail wheeling and transmission costs). Any such forward-looking statements should
be considered in light of such factors and others noted in the Companies' Forms
10-K for the year 2001, the Quarterly Reports on Form 10-Q for the quarters
ended March 31, June 30, and September 30, 2002 and other reports on file with
the Securities and Exchange Commission.
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act
of 1934, the registrants have duly caused this report to be signed on their
behalf by the undersigned hereunto duly authorized.
Dated: December 18, 2002
IDACORP, Inc.
By:/s/Darrel
T. Anderson
Darrel T. Anderson
Vice President, Chief Financial
Officer and Treasurer
IDAHO POWER COMPANY
By:/s/Darrel
T. Anderson
Darrel T. Anderson
Vice President, Chief Financial
Officer and Treasurer